Can anyone help me with why my dependent sections are working? I put them in correctly, and my master schedule shows all my classes are correct. When I go to load I get this:
Instead of completing Quarter 1 with all the classes, and then filling for each quarter, it is scattering them all around.
If I remember correctly, Dependent Sections do not work with the Load process in PowerScheduler. They should work with the Schedule Mass Enroll function in PowerScheduler.
We have 4 quarters. Do you know if there is a way to only schedule Quarter 1?
Hi @skleppert,
Your thread has been responded to here.