PowerScheduler: Dependent sections-Troubleshooting

skleppert
Trainee

PowerScheduler: Dependent sections-Troubleshooting

Can anyone help me with why my dependent sections are working?  I put them in correctly, and my master schedule shows all my classes are correct.  When I go to load I get this:

skleppert_0-1686767470108.png

 

Instead of completing Quarter 1 with all the classes, and then filling for each quarter, it is scattering them all around.  

 

3 Replies
JeffG9
PowerSchool Champion
PowerSchool Champion

If I remember correctly, Dependent Sections do not work with the Load process in PowerScheduler. They should work with the Schedule Mass Enroll function in PowerScheduler.

______________
Full Disclosure: I do not work for PowerSchool
skleppert
Trainee

We have 4 quarters.  Do you know if there is a way to only schedule Quarter 1? 

 

Reshma
Community Support Expert
Community Support Expert

Hi @skleppert,

 

Your thread has been responded to here.



Reshma
PowerSchool Community Support Expert

Remember to give Kudos to suggestions that help you!
If another user helps solve your issue, please select Accept As Solution on their post so others can see the solution, too!